Sample of Free Preliminary Design

For Reference Only

(Note:  This preliminary design did lead to a real project that is now in operation)

 

BWC Preliminary Design and Budget

Project:  FAA Chandalar Lake Hybrid System

  March 23, 1999

 

1.  Wind Resources:

The location and the altitude (442 m) correspond to a Class 1, > 4.4 m/s at a height of 10 m, wind zone according to the US-DOE World Wind Atlas. However, the DOE data for this area of Alaska is based on roof mounted anemometers and is conservative.  The DOE report states: “The map analyses represent the lower limits of the wind power resource for exposed areas”.  Therefore, we have assumed that the Chandalar Lake site resource is 4.8 m/s (10.8 mph) at a height of 10 meters.  For the average monthly wind speeds we have scaled data from an earlier project at Ft. Greely, which in turn, was based on NCDC data.

 

2.  Solar Resources

Solar resource data from Solarex and PVCAD were combined to establish monthly estimates of average daily insolation.  The annual average was estimated at 3.4 kWh/m2.  The summer resource is usable, but the winter resources are extremely low.

 

3.  Wind Turbine and Solar Array Performance

Wind turbine performance predictions are based on the battery-charging version of the BWC EXCEL wind turbine, which has a peak output of 7-8 kW.  The modeling was done with WindCAD; a printout is attached.  Please remember that the daily energy predictions are for DC kWh, not AC kWh, so the losses from storage and power conversion (DC/AC inverter) must be factored in before comparing them to the load or the diesel generation.

The wind turbine performance predictions assume 18 meter towers, a Weibull K = 2, an altitude of 300 meters, a wind shear exponent of 0.143, and 5% losses due to turbulence.  Predicted average daily energy production varies from 17 DC kWh in July to 50 DC kWh in December.

Solar array performance was modeled for an arbitrary 1 kW system using first-order (non-temperature compensated) efficiency estimates.  The resulting predicted average daily outputs for the 1 kW array varied from 0.1 kWh in December to 5.8 kWh in May.

The wind and solar resources have good seasonal complementariness.  The wind peaks in the winter and the solar peaks in the summer.  However, in general, the wind resources are predicted to be better than the solar resources.

 

4.  Load

The load is a constant 1,520 W AC communications load and a seasonal heating load, which has been calculated from temperature data.  Both NDB and heating loads have been converted to average daily demand by month.  All loads are assumed to be 120/240 VAC, 60 Hz, 1-phase.

 

5.  Sizing for Wind/Solar/Diesel Alternatives

Figure A shows the monthly performance spreadsheet used to evaluate the different hybrid system possibilities.  The model accounts for the DC subsystem losses for storage, power conversion, and customary deratings and allows the wind and solar subsystem sizes to be varied to evaluate the effect of these changes on overall system performance.  Due to the size of the load the model uses unit sizes of 7.5 kW for the wind turbine (based on the BWC Excel-R) and 1 kW for the photovoltaics. 

Figure A shows the basic performance for a 7.5 kW wind turbine and a 1 kW PV array.  The model predicts that this system would provide ~ 44% of the site’s annual energy (see Load Coverage, Annual Ave.).  The remaining ~ 56% of the energy would be supplied by the back-up diesel(s).

Generally, the least cost system will provide ~ 75% of the sites annual energy from renewables and ~ 25% from the diesel.  So, these targets are generally applied.  When looking at the renewable energy alternatives we like to compare only the renewable energy subsystem costs.  For wind these include the wind turbine(s), tower(s), tower wiring, charge regulator(s), and typical installation costs.  For solar these include the solar modules, array structures, wiring, charge regulator(s), and typical installation costs.  The common energy storage, energy conversion, and systems controls costs are excluded because they will be necessary regardless of the chosen renewable energy generation equipment.

Figure B shows the least cost all PV system.  An 14 kW PV array would provide ~ 58% of the annual energy at a subsystem cost (excluding the balance of systems: batteries, inverter, DC source center, etc) of ~ $126,000

Figure C shows the least cost all wind system.  A 15 kW (two Excel-R’s) wind component would provide ~ 78% of the annual energy at a subsystem cost (excluding the balance of systems: batteries, inverter, DC source center, etc) of ~ $70,000.

Figure D shows the least cost wind/solar hybrid capable of supplying a higher percentage of the sites’ power on an average basis.  The sizing is determined by minimizing the excess production during the high resource months.  This system would have 15 kW of wind and 5 kW of PV and would provide ~ 92% of the annual energy at a combined subsystem cost of ~ $115,000.

We recommend the system shown in Figure C: 15 kW of wind, no solar (click here to see what system the customer, the FAA, decided upon and installed. Use the "back" feature of your browser to return to this page)

 

6.  Preliminary Design and Budget

As shown in the attached one-line electrical schematic, BWC is recommending a system consisting of the following major elements:

  15 kW wind turbine, with 18 m guyed tower

  400A, 48 VDC DC Source Center

  100 kWh battery bank

  5.5 kW 120 VAC, 60 Hz, 1Ř inverter (with diesels control and reverse-mode battery charging)

  10 kW Diesel Generator

The budgetary estimate for the hybrid system is as follows:

 

            Equipment and Materials

                        Wind Turbines and Towers    US$ 51,000

                        Batteries (sealed)                        19,000

                        Inverter / Charger System               4,000

                        DC Source Center                         1,500

                        Diesel Generator                         16,000

                        Wiring Materials, etc.                    3,000

                        Special Tooling & Spares               1,500

                                Subtotal:                          $ 96,000

 

            Other Costs

                        Shipping                                                      $ 5,000

                        Equipment Building & Civil Works                   15,000

                        Misc. Material, Supplies, & Services                 5,000

                        Installation, Commissioning, & Training            12,000

                            Subtotal                                                  $ 37,000

 

                                Total:                        US$ 133,000

                       This includes the cost of a BWC supervisor for the installation, commissioning, and training. 

(Note: We underestimated the installation costs because we assumed the site was accessible by road and we didn't factor in permafrost.  In actual fact, the site was accessible only by air and permafrost was a significant problem. Fortunately, the FAA's construction company was able to construct more accurate budgets)