|
|
|
|
|
|
|
Carting Batteries to Town for Charging is a
Common Practice in Developing Countries |
|
Offering Wind/Diesel Powered Battery Charging
Services at the Village Appears to be Very Cost Effective |
|
Cost Of Service, Including Lights and Battery
Delivery Service, Ranges From $2.50 - $5.00 Per Month |
|
Profitable Public or Private Sector
Electrification, Even Serving The Very Poor, Is Possible With This
Technology |
|
|
|
|
Systems Operate Inefficiently Due To Low Load
Factors |
|
Power Is Not Available 24 Hours ... Limits
Economic Development (e.g.,Daytime Productive Uses) and Some Valuable
Applications (e.g., Refrigeration) |
|
Manual Controls and Dispatch - High Labor Costs |
|
Major Overhauls And Extended Downtime Are Common
... Total Abandonment Of Equipment Not Uncommon |
|
Continuing Headache of Fuel Supply |
|
Governments Often Have Goal Of Reducing Fuel Use
And Expenditures |
|
|
|
|
Characteristic Wind Diesel |
|
Capital Cost High Low |
|
Operating Cost Low High |
|
Maintenance Requirements Low High |
|
Available On-Demand No Yes |
|
|
|
|
|
|
Provide Dependable, Utility-Grade 24 Hour AC or
DC Power |
|
Not Dependent On Single Source Of Energy |
|
Flexible, Expandable, Able To Meet Changing
Loads |
|
Simple, Quick, Low Cost Installation |
|
Low Operating Costs (O&M and Diesel Fuel) |
|
Simple Operation, Low Maintenance & Service
Requirements |
|
User Not Required To Operate, Maintain, or
Repair |
|
Lower Life-Cycle Cost Of Electricity For Remote
Applications |
|
|
|
|
High Capital Cost Compared To Diesel Generators |
|
Diesel And Hybrids Have Very Different Cost
Components |
|
More Complex Than Stand-Alone Power Systems ...
Requires Battery Storage And Power Conditioning |
|
Not Yet In Full Commercial (High Volume)
Production ... Few Suppliers |
|
|
|
|
Very Small Systems (< 2 kWp Total) Usually Do
Not Use Back-up Generators And Have Relatively Larger Battery Banks (And
Usually Solar Modules) |
|
Larger Systems Usually Are Hybrid Systems With A
Diesel Generator (And Sometimes Solar Modules) |
|
New System Architectures: Rotary Converters And “AC Bus” Systems
Are Emerging for Larger Systems |
|
|
|
|
|
|
|
|
Inverter Is Often the Critical Component |
|
Inverter Technology Has Improved
Greatly in Last 5 Years ... Reliability
is Now Quite Good |
|
Features:
Charging, Low Battery
Cut Off, Diesel Synchronization
(Load Sharing) |
|
Small Units Still Mostly Modified
Square Wave Output ... Okay,
But Can Cause Noise in Light
Ballast's and in Communications
Equipment |
|
Units Above 3 kW Now Mostly Sinewave Output; THD
< 5% |
|
Efficiencies Run 80-94%; Average is ~90% |
|
Costs are Typically $0.60-1.00/W |
|
50 kW+, 3Ř Units Now Common |
|
For Village Power, Leading Suppliers are Trace
Engineering (U.S.) and Advanced Energy Systems (Australia) |
|
|
|
|
|
|
Flooded Lead-Acid Batteries
Still the Technology of Choice |
|
Deep-Cycle Batteries Required
- Vehicle Starting Batteries Last
Only 1-2 Years in Deep Cycle
Service |
|
Sealed Batteries Cost ~50%
More ... Too Expensive for
Most Village Power Situations |
|
Typical Efficiency is ~75%,
But Only 40-70% of Generation
Goes to Storage - Batteries Only
Take Net Power After Load |
|
Battery Costs are Typically $55 - 150/kWh |
|
Best Costs on Smaller Systems Achieved in Using
High-Volume Golf-Cart Batteries (eg., Trojan T-105: ~$45/kWh) |
|
|
|
|
Batteries Should Not be Discharged Below 80% ...
Usable Capacity is ~80% of Total Capacity |
|
Batteries Should be Equalized Approximately
Monthly |
|
Batteries are Connected in Series to Build
Voltage and in Parallel to Build Capacity |
|
Batteries Can be Paralleled Up to 5 Strings
Without Problems |
|
Battery Strings Should be Fused or Breakered to
Protect for Short Circuits |
|
Battery Acid Is a Serious Health Hazard |
|
Hydrogen Gas is Generated, Particularly During
Equalization |
|
The Variable Nature of Battery Charging with
Wind Power Seems to Have a Positive Effect of Operating Life |
|
|
|
|
DC Source Centers Eliminate the Bad Practice of
Attaching Sources and Loads Directly to the Battery Terminals |
|
Common Connection Point for All DC Sources,
Loads, and Storage |
|
Incorporates Fuses or Circuit Breakers for Major Components
... Providing Short Circuit Protection |
|
Often Constructed Around Multi-pole Switch,
Providing Main System Disconnect |
|
Usually the Inverter is the Primary Load |
|
Costs are $400 (1 kW) - $1,800 (20 kW), Costs
Primarily Determined by Current Levels |
|
Some Suppliers Offer Nice Power Metering Package
Options |
|
DC Bus Provides Easy Method for Paralleling
Multiple Wind Turbines and/or PV Arrays |
|
|
|
|
Typical Hybrid System Control
Functions: • Battery
Overvoltage ... Wind & PV Regulators
• Battery Undervoltage (Load
Shedding) ... Inverter
• Battery Equalization ...
Wind & PV Regulators
• Back-up Generator Start /
Stop ... Inverter or DC Source Center |
|
Centralized Controller Which Monitors
All Sources and Loads is Not
Necessary |
|
Most Controls Triggered by DC Bus
Voltage (Battery Bank Voltage) |
|
State-of-Charge Monitors or Energy Counting
(e.g., Net Ampere-Hours)
Controls Don’t Work as Well |
|
Some People Prefer to have Manual Back-up Power,
Controlled by Local Operator |
|